Report for week 9.

M2 was lifted Sunday morning from floating crane, but because it was historic low level in the river, the crane did not get in suitable position to unload on the ground prepared for M2.

During the week the MCF has used their imagination to get M2 into her final position. Using train wheels and the hydraulics from an earth mover they now have only a few meters left. .

During the week we have used a lot of time planning for the exhibition to be held in week 10 and 11.
Our goal is to get publicly and get a main sponsor for the project, and to start the auction of the two paintings.

In the coming two-three weeks there focus will be on building a shed for M2, and to continue raising money from private interests, funds and legates.

This week we also maid a list of the efforts and gifts to the project so far. This list is not yet ready, but it is so far thousands of hours and at least 3 mill NOK.

2665
Erik Berg